Dear Pri Tari Team,

Thank you for your purchase! Our teams are preparing your order, so we can install the floors in Israel on the discussed date. On this page you can track your order, see when we need your input, and follow the steps until the installation date. When your order moves on to the next phase, you will receive an e-mail with the update. 

Kind regards,
Melissa Koenders

1. Complete order

 

Before the materials are produced, our work planner, Jeffrey Sturrus, will prepare the definitive working drawings. E.g., drawing up the final rooms, calculating the surface area, finalising the detailing, and determining colours per room.
After this is complete, the project manager, Elbert Boon and his assistant, will make the planning, determine the application team, and place the order for production.

Questions? Please contact Melissa Koenders 
Any H&S, method statement related questions? Please contact Jeffrey Sturrus

What information do we still need from you?

Could you please advise if any H&S documents are required to execute the works?

Please send the above information to project support by return, so the order can be processed and move forward to production. 
Checking and processing after receipt of the missing information takes 3 - 5 working days.

 

2. PRODUCTION

Starting date production:  June 13, 2022.

Our materials are produced in our own factory. As soon as the raw materials are delivered, production starts and the components are prepared. Production takes up to 3 working weeks.
All consumables and tools that are needed on location are also collected in this phase.

 

  • Bolidt Production facilityCredits: Bolidt Production facility
  • Bolidt productie Bolidtop 700Credits: Bolidt Production facility
  • Bolidt productie Bolidtop 700Credits: Bolidt Production facility
  • Bolidt productie Bolidtop 700Credits: Bolidt Production facility
  • Bolidt productie Bolidtop 700Credits: Quality check by R&D
  • Bolidt productie Bolidtop 700Credits: Quality check by R&D
  • Bolidt toolboxCredits: The tools are collected
  • Bolidt toolboxCredits: The tools are collected
  • Bolidt toolboxCredits: The tools are collected
  • Bolidt toolboxCredits: The tools are collected

3. TRANSPORT

Estimated time of arrival at the port of Ashdod: July 11, 2022.

In addition to the actual transport, the necessary paperwork is also arranged here. Your contact person at logistics, Marcel Venhuizen, takes care of the administrative processing. He will contact you to arrange all documents.

Questions? Please contact Marcel Venhuizen

 

  • Bolidt Logisitcs - Marcel VenhuizenCredits: Marcel Venhuizen
  • Bolidt warehouse
  • Bolidt magazijn Bolidtop 700
  • Bolidt magazijn Bolidtop 700
  • Bolidt magazijn Bolidtop 700
  • Bolidt logistics
  • Bolidt magazijn Bolidtop 700

4. INSPECTION

Expected inspection date:  September 21, 2022

Before the application team can get to work, the project manager, Elbert Boon, will visit your site for an inspection. We would like to schedule the site meeting after the concrete has poured and the building is weather protected.
After the inspection, you will receive a report with points off attention that need to be arranged before the application team can start. Then Elbert Boon gives a final GO on the project.
The operations assistant, will book the plane tickets and overnight stays for the team and apply for the necessary visas and work permits.

Questions? Please contact Elbert Boon

  • Bolidt operations Elbert BoonCredits: Elbert Boon
  • Bolidt inspection

5. application

Expected starting date of the project is: October 9, 2022

Yes, the moment you’ve been waiting for... The Bolidtop 700 will be applied layer by layer. The application team is attuned to each other, efficiency and craftsmanship come together here.

 

6. Completion of the works

Estimated date of completion of the works: October 28, 2022.

The work is completed, all tools are packed again, the site shall be left behind in a clean state. After inspection by the foreman, he will do the handover with you. Our foreman will go through the areas with you and ask you to sign the completion certificate.
He will contact you to make an appointment.

To maximise the lifespan of your floor you find  the cleaning instructions here.


MEET THE TEAM

We develop, produce and apply our synthetic flooring systems ourselves. The unique integrated value stream enables Bolidt to be a partner who thinks along, advices and takes on challenges. All expertise under one roof!
Good for you, because that way we can keep the lines of communication short.
Below you can meet the team that ensures that everything runs smoothly and contact them directly if you have any questions along the way. 

 

Bolidt Dennis van Grevenbroek - poultry specialist

Dennis van Grevenbroek
Sales


Get in touch with me?
Call +31 6 46 09 47 82

E-mail

Bolidt Melissa Koenders - poultry

Melissa Koenders
Sales


Get in touch with me?
Call +31 78 684 54 08

E-mail

Bolidt operations Elbert Boon

Elbert Boon
Project manager


Get in touch with me?
Call +31 6 53 85 98 34

E-mail

Bolidt - Team operations assistenten

Team Operations Assistants


Get in touch with us?
Call +31 78 684 54 35

E-mail

Bolidt Project support - Jeffery Sturrus

Jeffery Sturrus
Project Support


Get in touch with me?
Call +31 78 684 54 49

E-mail

Bolidt Logisitcs - Marcel Venhuizen

Marcel Venhuizen
Logistics


Get in touch with me?
Call +31 78 684 54 38

E-mail